Steel Supporting structure for concete panels
Crain placing panel into place
Supports fixed to pads in ground. Tied with bolts.
Tuesday, May 29, 2007
Monday, May 28, 2007
Wednesday, May 16, 2007
South Yarra Developement (2)
Rio bars grouted around base to bring up to slab level.
Pipework extruding from slab has membrane surroud to accomodate for slab contraction. Also note the cut lines in slab to allow for walls to be recessed.
Lift core shown once timber formwork has been removed, also in background the white expansion membrane between slab and neighbouring.
Pipework extruding from slab has membrane surroud to accomodate for slab contraction. Also note the cut lines in slab to allow for walls to be recessed.
Lift core shown once timber formwork has been removed, also in background the white expansion membrane between slab and neighbouring.
Wednesday, May 9, 2007
BDC Project - Archi (3)
South Yarra Developement
Trench mesh for slab tied together. Timber formwork to the edges with the waterproof sheeting to the base
Close up of the mesh showing the beams/ sprips to the base of the slab. note the reinforcement rods tied to mesh
Rio bars for possible column tied into mesh.
Rio bars exposed out of slab, internal filled in with slurry mix after slab hardened.
Close up of the mesh showing the beams/ sprips to the base of the slab. note the reinforcement rods tied to mesh
Rio bars for possible column tied into mesh.
Rio bars exposed out of slab, internal filled in with slurry mix after slab hardened.
Wednesday, May 2, 2007
BDC Project - Archi (2)
This image is how i want my column trasition to look like. The truss overhead is pre-welded to the column and fitted onto concrete columns for a stronger presence at graoud level to accomodate for truck.
The idea is too appear as organic as possible using the steel on the outside and change to a combination of timber and steel on the inside
Detail of the top section with the steel column being welded to the trusses.
The idea is too appear as organic as possible using the steel on the outside and change to a combination of timber and steel on the inside
Detail of the top section with the steel column being welded to the trusses.
BDC Project - Archi
These top three renders outline my building form. The red indicates the office area & orange the factory. I have started to show the concrete columns and overhead steel structure for the factory. The colunms will join the structure through the use of steel branching its way up to the as per the Enrik Miralles model below.
I propose to make the bottom level a nutral stone material typical to Geelong and use timber in the upper areas to create vents for air circulation.
Friday, April 13, 2007
Mount Buller 3 Construction
Double brick retaining wall, to have crushed rock added.
Large retaining wall with steel structure for ski access to the building.
Ag drain to run around the base of the slab, it will have to be connected to site drainage before completion.
Battered earth to back of retaining wall, loose pipes and water at base where ag drain is located or base gutter.
side angle of batter with retaining wall on left. note the moisture in the earth and drainage required to base of retaing wall.
Large retaining wall with steel structure for ski access to the building.
Ag drain to run around the base of the slab, it will have to be connected to site drainage before completion.
Battered earth to back of retaining wall, loose pipes and water at base where ag drain is located or base gutter.
side angle of batter with retaining wall on left. note the moisture in the earth and drainage required to base of retaing wall.
Mount Buller 2 Construction
Reinforcing for a angular column to be formed out and poured onsite.
piping to rear of building where possible kitchen will be located, note the lengths stick ing out of the poured concrete.
view looking down lift shaft, angulal cross bracing for builders to stand on. you can also see pattens from the form work on the concrete.
retaining wall: crushed rock is layed at bottom for drainage... in this application it is about 1m high
timber form work above for concrete slab and retaining wall at base.
piping to rear of building where possible kitchen will be located, note the lengths stick ing out of the poured concrete.
view looking down lift shaft, angulal cross bracing for builders to stand on. you can also see pattens from the form work on the concrete.
retaining wall: crushed rock is layed at bottom for drainage... in this application it is about 1m high
timber form work above for concrete slab and retaining wall at base.
Mount Buller Construction
Timber members & steel scaffold hold up ply wood as form work for a concrete base.
Inside the building bondek
is supported by the concrete block walls and steel scaffold in the centre.
Timber stud walls are used for non loadbeaing areas, pipe work is precut through the bondek before the concrete is poured.
Wednesday, April 4, 2007
ceiling framing
this pic shows the detail of a suspended ceiling. It also shows how the electrical wiring is running on support, the column is used to run electricty to the floor level below
This shows the roof structure supported on the concrete bricks and how the connection of the suppended ceiling meets the wall.
Steel roofing members and supports for suspended ceiling
supprt column is filled in with concrete bricks
external gutter detail, the gutter supprted in steer brackets
This shows the roof structure supported on the concrete bricks and how the connection of the suppended ceiling meets the wall.
Steel roofing members and supports for suspended ceiling
supprt column is filled in with concrete bricks
external gutter detail, the gutter supprted in steer brackets
Wednesday, March 28, 2007
Week3 Composite
Tuesday, March 27, 2007
Harbour Bridge Details
Subscribe to:
Posts (Atom)